You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.
Home > Solar Kit Support > Solar Charging Kit Support > Solar Kit Installation: Initial Connection & Operation
Solar Kit Installation: Initial Connection & Operation
print icon

Installation Steps 

 

  1. Check all electrical connections and ensure all cables are securely fastened.
  2. Install the 30A Fuse into the fuse holder, ensure the fuse holder is securely fastened.
  3. Remove the opaque material from the solar panels.
  4. Follow the PWM 30 operating steps.

Products covered in this article: Overlander/Overlander (E)/Retreat/Retreat (E)/Weekender/Solar Elite/Solar Extreme Solar Kits

Feedback
0 out of 4 found this helpful

scroll to top icon